Symptom
Your requirement is to migrate Projects, but you receive the below error during the Simulation step:
Conversion rate must not be greater than 24
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to Business Configuration work center
- Select Implementation Projects view or Overview
- Search and Open the activity Migration of Projects
- Select Migrate projects using the migration tool
- Upload the Migration File
- Execute Migration for the respective Migration File with Migration Mode Add new records
- You receive the error message mentioned during the Simulation step
Cause
In the Project Plans sheet, you maintained data as below:
Unit of Work as Working days
Hours per Working Day as 365
For the field Hours per Working Day, if you use Working days as Unit of Work, enter the number of hours that add up to one working day. As we have 24 hours in a day, the field Hours per Working Day should contain value 24 or lesser.
Resolution
Correct the data in the Migration File and proceed with the migration activity.
Keywords
Unit of Work, Hours per Working Day, Migration of Projects, Conversion rate must not be greater than 24 , KBA , conversion rate must not be greater than , migration of projects , hours per working day , unit of work , AP-PRO , Project Processing , Problem