Symptom
How to track changes made to a billing proposal or Debit Memo Request (DMR).
Environment
- SAP ERP Project System (PS)
- SAP S/4HANA, Cloud
Resolution
In Project Systems (PS), there is no possibility to trace changes to the billing proposal - this functionality does not exist in standard. However, Sales & Distribution (SD) billing allows the option to trace changes to a DMR following the below steps:
- Run app 'Manage Debit Memo Requests'(F1988).
- Display a Debit Memo Request by clicking the number.
- Select menu path 'More' → 'Environment' → 'Changes'.
See Also
SAP documentation Debit Memo Request
Keywords
billing proposals, SD, activity log, trace, F1848, F1988, app , KBA , PS-FIO-REV , Fiori UI for Project Systems-Revenues and Reso. Rel. Billing , SD-BIL , Billing , PS-REV , Revenues and Eamings , PS-FIO-REV-2CL , Please use PPM-SCL* , How To