Symptom
Many or single procurement proposals like planned orders are created at the end of the planning time fence if fixed MRP types is set in the material master, like MRP type P1 or P3.
So, the requirement shortage dates and the dates of procurement proposals don't match.
Read more...
Environment
- Production Planning (PP)
- SAP R/3
- SAP R/3 Enterprise 4.7
- SAP ERP Central Component
- SAP ERP
- SAP enhancement package for SAP ERP
- SAP enhancement package for SAP ERP, version for SAP HANA
- SAP S/4 HANA
Product
SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions
Keywords
P2, P3, P4, material requirements planning, purchase requisition, schedule lines, stock requirements list. , KBA , PP-MRP-PP , Procurement Proposal , How To
About this page
This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).Search for additional results
Visit SAP Support Portal's SAP Notes and KBA Search.