2696717 - Downtimes and capacity variants not considered by SNP heuristic when creating SNP planned orders

Symptom

You have maintained a downtime, a capacity profile or a capacity variant to define a non availability of a production resource on a working day of the factory calendar. SNP heuristic creates planned orders ignoring this restriction.


Read more...

Environment

  • SAP Supply Chain Management
  • Advanced Planner and Optimizer
  • Supply Network Planning (SNP)
  • SNP Heuristic

Product

SAP Supply Chain Management 2005 ; SAP Supply Chain Management 2007 ; SAP Supply Chain Management 4.0 ; SAP Supply Chain Management 4.1 ; SAP Supply Chain Management 7.0 ; SAP enhancement package 1 for SAP Supply Chain Management 7.0 ; SAP enhancement package 2 for SAP Supply Chain Management 7.0 ; SAP enhancement package 3 for SAP Supply Chain Management 7.0

Keywords

  • Scheduling
  • Resource
  • Ressource
  • Kalender
  • Calender
  • Fabrikkalender
  • Holiday
  • Shutdown
  • block planning
  • Fabrikferien
, KBA , SCM-APO-SNP-HEU , SNP Heuristic Planning , Problem