Symptom
- When a single lower-level WBS element is opened directly in CJ20N (without the project hierarchy), changing basic start and finish dates does not update higher-level WBS dates.
- Information message CJ175 is displayed when saving.
- If the same WBS element is opened from within the project structure, dates are inherited upwards as expected and CJ175 does not occur.
"Image / Data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental"
Read more...
Environment
- SAP ERP Project System (PS)
- SAP R/3
- SAP R/3 Enterprise
- SAP ERP Central Component
- SAP ERP
- SAP Enhancement package for SAP ERP
- SAP Enhancement package for SAP ERP, version for SAPrson 1>
- SAP S/4HANA, on-premise
- Time Scheduling
Product
SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions
Keywords
project profile, scheduling scenario 1, WBS roll-up, date inheritance, single-object processing, hierarchy not loaded, PS scheduling, basic dates, date propagation, ECC PS, S/4HANA PS, CJ29 scheduling, CJ02, CJ03 , KBA , PS-DAT-WBS , Time Scheduling , PS-ST-WBS , Work Breakdown Structure , Problem