2700369 - CJ20N: Bottom-up scheduling does not roll up dates from a lower-level WBS opened alone; higher-level dates are not updated and message CJ175 is shown.

Symptom

  • When a single lower-level WBS element is opened directly in CJ20N (without the project hierarchy), changing basic start and finish dates does not update higher-level WBS dates.
  • Information message CJ175 is displayed when saving.
  • If the same WBS element is opened from within the project structure, dates are inherited upwards as expected and CJ175 does not occur.

"Image / Data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental"


Read more...

Environment

  • SAP ERP Project System (PS)
  • SAP R/3
  • SAP R/3 Enterprise
  • SAP ERP Central Component
  • SAP ERP
  • SAP Enhancement package for SAP ERP
  • SAP Enhancement package for SAP ERP, version for SAPrson 1>
  • SAP S/4HANA, on-premise
  • Time Scheduling

Product

SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions

Keywords

project profile, scheduling scenario 1, WBS roll-up, date inheritance, single-object processing, hierarchy not loaded, PS scheduling, basic dates, date propagation, ECC PS, S/4HANA PS, CJ29 scheduling, CJ02, CJ03 , KBA , PS-DAT-WBS , Time Scheduling , PS-ST-WBS , Work Breakdown Structure , Problem

About this page

This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).

Search for additional results

Visit SAP Support Portal's SAP Notes and KBA Search.