Symptom
When you change a Task duration you expect the header task of that Project to be updated accordingly.
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to Project management work center
- Go to Projects view
- Search for respective Project
- Open the Project
In the project plan in the Gantt chart, you see that header task duration is Smaller than the highest duration task.
Cause
Since you maintained finish date as well as start date system cannot update the header task automatically because there is hard stop by mentioning finish date as to when the project has to finish. So here finish date cannot change until you manually change it.
Resolution
If you want system to change the Header Task duration either mention only start date ( forward scheduling)or only finish date( backward scheduling).
Keywords
Project task Duration Not Updated, Project task Duration Not changed , KBA , AP-PRO , Project Processing , Problem