2718035 - Project creation gives message: "The cost center is not valid for these dates"

Symptom

Message "The cost center is not valid for these dates" is displayed when trying to create an internal project or a customer project.

Environment

SAP S/4HANA Cloud

Reproducing the Issue

  1. Go to App: Create Internal Projects or Create Customer Projects.
  2. Error-Message is displayed: The cost center is not valid for these dates.

Cause

There is no cost center configured for the service organization.

Resolution

  1. Go to App: Maintain Service Organizations
  2. Open the Service Organization in Edit-Mode
  3. Select in the drop-down field "Default Cost Center"
  4. Save changes.

Keywords

/CPD/SC_INTPROJ_MONTIOR_SRV, SAP_PSP_BC_INT_PRJ_MONITOR_PC, SAP_PSP_BCG_INT_PRJ_MANAGE_PC, SAP_BR_PROJ_MANAGE_COMM, /CPD/SC_PLAN_INT_PROJ_SRV, /CPD/SC_DEFINE_SERVICE_ORG_SRV, SAP_PSP_BC_MASTER_DATA_PC, F1656, F1421 , KBA , CA-CPD-SS , S/4HANA Public Cloud – Professional Service Projects , Problem

Product

SAP S/4HANA Cloud Public Edition all versions ; SAP S/4HANA Cloud all versions