Symptom
Message "The cost center is not valid for these dates" is displayed when trying to create an internal project or a customer project.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
-
Go to App: Create Internal Projects or Create Customer Projects.
-
Error-Message is displayed: The cost center is not valid for these dates.
Cause
There is no cost center configured for the service organization.
Resolution
-
Go to App: Maintain Service Organizations
-
Open the Service Organization in Edit-Mode
-
Select in the drop-down field "Default Cost Center"
-
Save changes.