Symptom
The Starting Value of Maintenance Plan shows wrong format.
Environment
SAP Cloud for Customer.
Reproducing the Issue
-
Go to the Installed Base work center.
-
Go to the Maintenance Plan view.
-
Search and open maintenance plan ABC1 (where ABC1 is the maintenance plan name).
-
Go to the Plan Definition facet and click on button Add Group .
-
In the Add Condition Group window which opens, enter value under field Starting Value.
You will see it comes in format yyy.yyy.yyy (where y is any numberic value ).
Cause
For Starting Value ,we consider the time unit Day/Month/Week/Year. This is taken from the time unit maintained for the Value field but is just a numeric value and for large value it will show in format as yyy.yyy.yyy
Resolution
This is an expected system behavior.
Keywords
Maintenance Plan, Plan Definition , KBA , LOD-CRM-MPL , Maintenance Plan Processing , Problem
Product
SAP Cloud for Customer add-ins 1811