Symptom
-
You create a sales quote with project reference.
-
The Project has the referenced item maintained with Unit ZZZ (representative for Unit type).
- The sales quote determines Unit YYY (representative for Unit type).
Environment
SAP Business ByDesign
Reproducing the Issue
-
Navigate to the New Business workcenter.
- Open the New Sales Quote view.
- Maintain relevant data, as account and sales unit.
- Click on Create with Reference.
- Select Project ABC (ABC represents the Project ID).
- Click on OK.
The item data retrieved from the project is set up with Unit YYY.
In Project ABC the tasks are set up with Unit ZZZ.
Cause
-
There is currently an incorrect determination of the Unit of Measure, when creating a Sales Quote with Reference.
- Because the Unit of Measure cannot be determined from the project, the data is determined from product master data.
- In this case Unit ZZZ is maintained as the Unit of Measure in the product master data.
- The Quantity is transferred correctly.
Resolution
-
This will be reviewed in a future release, so that the Unit of Measure is correctly transferred from project to the sales quote.
- Maintain the Unit of Measure in the Sales Quote manually.
Keywords
Unit of Measure, Project reference, Sales Quote, Mengeneinheit, Projektreferenz, Angebot , KBA , AP-CQP-CQ , Customer Quote , Bug Filed
Product
SAP Business ByDesign 1811 ; SAP Business ByDesign 1902