SAP Knowledge Base Article - Public

2733655 - How to Change From Operating Time to Shift Program for an Equipment Resource

Symptom

You migrate Equipment Resources using the migration template. In this template, you maintain "418 - Shift Program" in the column Active Operating Time Type. However, after the migration, the system defaultes this to "422 – Operating Time", and when you try to change this in the application, the system throws the error message: "Changing the time type not possible; delete the maintained data first".

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to the Business Configuration work center.
  2. Navigate to the Implementation Projects view.
  3. Select the relevant Implementation Project and click the Open Activity List button.
  4. Find and select the Migration of Equipment Resources Activity.
  5. Click the Open button, to open the Migration tool.
  6. Find and select the relevant Source File ABC (ABC represents the Name of the Source file).
  7. Open the file ABC by clicking the Hyperlink.
  8. Click Edit.
  9. Go to the tab Std Operating Times.
  10. Enter the code "418" in the sub-tab Active Operating Time Type.
  11. Save and Execute the Migration.
  12. Go to the Supply Chain Design Master Data work center.
  13. Navigate to the Resources view.
  14. Find the relevant Resource XYZ (XYZ represents the Resource ID).
  15. Click Edit.
  16. Go to the Operating Times tab.
  17. You can see that Operating Time Type is defaulted to "Operating Time" and when you change it to "Shift Program", you get the error message: "Changing the time type not possible; delete the maintained data first".

Cause

You are experiencing this because you have not deleted the maintained Operating Hours. You must first remove the maintained Recurrence Pattern.

Resolution

Please follow below steps for changing the Time Type from "Operating Time" to "Shift Program" for a Resource:

  1. Go to the Supply Chain Design Master Data work center.
  2. Go to the Resources view.
  3. Find and select Resource XYZ.
  4. Click Edit.
  5. Go to the Operating Times tab.
  6. Select the Recurrence Pattern and remove it.
  7. Then select "Shift Program" instead of "Operating Time".
  8. Save your changes.

Keywords

Recurrence Pattern, Supply Chain Design Master , KBA , AP-RDM-ER , Equipment Resource , How To

Product

SAP Business ByDesign all versions