Symptom
When trying to change a project from status Contract preparation to In Execution you get the error below:
- Enter rate XXX/YYY rate type ZZZZ for MM/DD/YYYY in the system settings.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Go to Plan customer projects app.
- Select a project and click edit.
- Change the status of the project to "In Execution".
Cause
The exchange rate is not correctly maintained.
Resolution
Please follow the resolution of KBA 2705816.
Keywords
Exchange rate, system settings, Contract Preparation, In execution, project, customer project, plan customer project, create customer project, error, Maintain Exchange Rates, status, project status , KBA , CA-CPD-SS , S/4HANA Public Cloud – Professional Service Projects , Problem
Product
SAP S/4HANA Cloud Public Edition all versions ; SAP S/4HANA Cloud all versions