Symptom
It is required to save the configuration changes made in SSCUI-s to separate transports / change projects without releasing any project to the P-system.
Environment
SAP S/4HANA Cloud Public Edition
Cause
It is not possible to have several parallel transport requests/change projects active at the same time, as the complete dependency matrix for all objects was not yet developed. Therefore, it cannot be estimated, if a single transport would reach the P-system without disruption of the productive usage.
Resolution
It is currently not possible to have different transports/change projects during the same sprint. The configuration changes can only be saved to the sole active change project/transport.
If it is unavoidable to split the configurations to different change projects first release the changes to the P-system and afterwards create a new project for the rest.
See Also
KBA 2707813 - SAP S/4HANA Cloud Public Edition: Configuration Transport import time to P system
Keywords
Self-Service-Configuration-UI, deploy, Q2P, framework, cycle , KBA , SV-CLD-SSC , Self-Service-Configurations-UI , SV-CLD-FRM-INF , Implementation Framework Infrastructure , Problem