Symptom

You created an Actual Cost Release Run, and you can see that there are several warning messages that says: 'Action RELEASE not permitted for status Released'.

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to the Inventory Valuation Work Center.
  2. Select the Actual Cost Release view.
  3. Open the Run ABC (ABC represents the Actual Cost Release run ID).
  4. Click the Messages tab.
  5. You can see the warning messages: 'Action RELEASE not permitted for status Released'.

Cause

When checking the Not processed tab, you can see that all of the Materials appearing in this tab, are also appearing in the tab Messages. The warning is appearing: "Action RELEASE not permitted for status Released".

Those materials were not included because they already have a cost that was calculated in a released cost estimated.

Resolution

The costing process is always multilevel. That is, the system costs (or attempts to cost) all materials at all levels of the structure. As per indicated warning message, those materials may already have a released cost estimate. Since, released cost estimates cannot be recalculated, those materials are also appearing in the Not Processed tab.

See Also

Help Document: Material Cost Estimate Runs.

Keywords

Inventory Valuation, Costing Process, Actual Cost Release Run, Warning message, released cost estimated, materials, not processed tab. , KBA , SRD-FIN-INV , Inventory , How To

Product

SAP Business ByDesign all versions