2755260 - How to add new shifts overwritten factory calendar's validity date

Symptom

In App: Manage Work Center Capacity, new shifts that are not in factory calendar's validity date cannot be added successfully.

Environment

  • Production Planning (PP)
  • SAP S/4HANA Cloud

Reproducing the Issue

  1. Go to App: Manage Work Center Capacity
  2. Select a work center and go to detailed screen
  3. Add shift in 'Edit' mode

Resolution

Please tick indicator 'Overwrite Factory Calendar' if you would like to add new shifts to overwrite factory calendar's validity date.