Symptom
When changing the Stage of an internal project from 'Completed' to 'Closed', the error "Balance of WBS XXXXXXX.X.X is not zero" is raised.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Open the affected internal project.
- Change the Stage from Completed to Closed.
- Save the project.
Cause
The project costs have not been completely settled.
Resolution
- Costs can be settled by using the Run Settlement-Actual app.
- Please refer to scope item 1A8 for more details.
Note: If the user does not want to settle the costs before closing the Project, the user can also adjust the Settlement Profile of the Project to not relevant for Settlement.
See Also
Keywords
Costs, projects, internal project, settle, actual, closed, finished, cloud, WBS, stage, error, completed, settlement, 1A8, closed status, competed status , KBA , CA-CPD-SS , S/4HANA Public Cloud – Professional Service Projects , CO-OM , Overhead Cost Controlling , Problem