Symptom
When changing the Stage of an internal project from 'Completed' to 'Closed', the error "Balance of WBS XXXXXXX.X.X is not zero" is raised.
Read more...
Environment
SAP S/4HANA Cloud Public Edition
Product
SAP S/4HANA Cloud Public Edition all versions
Keywords
Costs, projects, internal project, settle, actual, closed, finished, cloud, WBS, stage, error, completed, settlement, 1A8, closed status, competed status , KBA , CA-CPD-SS , S/4HANA Public Cloud – Professional Service Projects , CO-OM , Overhead Cost Controlling , Problem