Symptom

System triggers error when you are trying to change the End date of recurrence for a Planning Run DEF (DEF refers to Planning Run id)

End Date should not be greater than KLM(KLM refers to Date and time)
Save failed

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to Supply Planning Work Center
  2. Navigate to Planning runs under Automated Actions View
  3. Select Run DEF  and Select Schedule
  4. In Schedule Job screen, Select Recurrence under Schedule
  5. Select "By the Minute", Start date/time would be defaulted with Current Date and Time
  6. Change "End date" for more than 60 days

Error appears as mentioned in symptom section

Cause

End date is mandatory for recurrent job and cannot be more than 60 days from start date.

Resolution

Set End Date as less than or equal to 60 days. By default end date will be set as 30 days from start date, if no input for end date is provided.

Note: Starting from 1902 Upgrade all Test Tenants will not have "No End Date" for  MDRO Jobs Recurrence Field, However currently this is not applicable for production  tenant i.e In Production Tenant for MDRO Jobs we still can set "No End Date" in Recurrence.

Keywords

End Date should not be greater than, Save failed, Recurrence End date/time,No End Date in Recurrence,Error appears when trying to change the Planning Run Recurrence for more than 60 days , KBA , no end date in recurrence field , end date should not be greater than , AP-SDM-MSD , Material Supply and Demand View , Problem

Product

SAP Business ByDesign all versions