Symptom
Tooltip for Assignment in Resource Scheduler shows data differently for different Assignments created.
Environment
SAP Cloud for Customer
Reproducing the Issue
-
Go to Resource Scheduler WorkCenter
- Then to Resource Scheduler View
- Click on the Gear icon option and select Settings
- Enable the field "Show Tooltip for Assignment"
- Now on hovering on any assignments created
The data display formats looks different for different assignments.
Cause
Tooltip data display differs for Grouped Assignments and Normal Assignments. And they are different compared to the Assignment bar data.
Resolution
For Grouped Assignment , the tooltip shows Customer Name, Customer Location. And for Normal Assignment, the tooltip shows Description, Customer Name. This is the expected system behavior.
Keywords