Symptom
You created the Planning Run XXX, however it does not plan the brand new product which were never planned before.
XXX = Planning Run ID
Environment
SAP Business ByDesign.
Reproducing the Issue
- Go to Supply Planning work center.
- Select Planning Runs view.
- Find the Run XXX.
- Select Schedule.
- Select Start Immediately.
- Choose Save and Close.
The new Application Log created is successful, however the new product is not planned.
Cause
The system is working as designed, the Planning Run will not automatically plan the product for the first time. You need to do it manually and then the Planning Run will work normally.
Resolution
- Go to Supply Planning work center.
- Select Products view.
- Find the relevant new Product.
- Select the new Product.
- Click Open.
- Select Run Planning.
- Choose Single or Multi BoM Level.
- Click Ok.
The proposal will be created manually.
See Also
2504532 - System Not Creating Planning Proposals via Automated Planning Run