Symptom
You work with Flexible Workflow for Purchase Contract.
Change of purchase contract during approval is not possible. But it is possible to change the released/rejected contract.
In this case there is a logic; checking what was changed in the contract. This is by comparing the changed fields with the fields of a reference structure.
In the App Manage Purchase Contract, there are 4 relevant fields which are editable, so changes on them will retrigger the workflow.
Environment
S/4HANA Cloud
Resolution
These are the relevant fields which retrigger the workflow based on the document type
Validity end date - Quantity & Value Contract
Material Group - Quantity & Value Contract
Target Quantity at item level - Quantity Contract
Target Value - Value Contract
The other way for the workflow is going to process again is in the LMEOUTP1C include into the me->fill_cekko.
Every field inside of the CEKKO will be checked to compare the old CEKKO and new CEKKO, and If they are different, the workflow will be going to approval again.
The Method FILL_CEKKO of Include LMEOUTP1C. Here the system fills the OLD structure and the new structure.