Symptom
Due to some business need, you need to extract a report for a bigger period than a week. Is it possible?
Environment
SAP SuccessFactors HCM Suite
Cause
There is a designed limitation on the Audit Reports maximum period, this is designed on this way to avoid performance issues on creation of long reports.
Resolution
You can find the maximum time range that change audit report covers on this Help portal page, currently it is seven days.
In case you need/want to audit changes over a longer period of time, you need to create multiple reports.
For example, if you want to audit changes made over the course of a month, run four separate reports of seven days each.
Keywords
KBA , LOD-SF-PLT-AUDR , Request Audit Report (Not Change Audit) , How To
Product
SAP SuccessFactors HXM Suite all versions