Symptom
When creating a new material with Accounting view, you want to change Price Control to V - Moving Average Price . However, the Price Control field is grey out. You can't modify it.
Environment
- SAP S/4HANA Cloud
Cause
Due to plant customizing, Price Determination is set to 3 by default.
With the activation of Actual Costing scoping item 33Q, the price determination is set to '3' by default, but can be changed on material level.
Please also refer to Note 721360.
Resolution
You can first change the field Price Determination from 3 to 2 and press "Enter". Then the field Price Control is available to edit.