Symptom

You made settings in SSCUI 102427 (Define Cost Component Structure) for Structure Y1. Afterwards, you check the Cost Component Group values in App Production Cost Analysis and found the values are not correct.

Environment

SAP S/4HANA Cloud Public Edition

Reproducing the Issue

Check Cost Component Group values in App Production Cost Analysis.

Cause

SAP Pre-delivered content comes with 2 Cost Component Structures:
1. Y1 - Used for Standard Costing
2. YP - Used for Reporting

The App Production Cost Analysis uses Cost Component Structure YP. The difference between YP and Y1 is the WIP accounts in YP (line 302)
With this it's possible to know the WIP via this App.

Resolution

Do the same changes you have done to Cost Component Structure Y1 , also to YP (except WIP).