Symptom
The Total Cost column in the Project's Material tab is not getting populated. Costs are properly assigned to Project.
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to the Project Management work center.
- Go to the Projects view.
- Search for Project ABC (ABC represents the ID of the Project).
- Click on Edit button.
- Go to the Materials tab.
- Click on the Avatar button.
- Select the option Start Personalization Mode.
- Expand Unnamed Table.
- Mark the box for Total Cost field.
- Click on Save button.
- Click on the Avatar button.
- Select the option Stop Personalization Mode.
- Go to the Materials tab.
Total Cost column is not populated with any costs for materials.
Cause
Issue is happening due to not initiated the cost calculation manually.
Resolution
- Go to the Project Management work center.
- Go to the Projects view.
- Search for Project ABC.
- Click on Edit button.
- Click on Valuate button.
This action will calculate the costs for entire project.