2813293 - Project Builder: dates not copied from template project

Symptom

In the Project Builder app, when creating a project by copying from a template project, the start and end dates are not copied from the template project, despite a warning message stating that the date will be copied from the source project

"Start and end dates are set based on the duration of the source project. Message no. CJ234"


Read more...

Environment

  • SAP ERP Project System (PS)
  • SAP S/4HANA, on-premise
  • SAP S/4HANA, Cloud

Product

SAP S/4HANA Cloud Public Edition all versions ; SAP S/4HANA all versions

Keywords

CJ234, CJ 234, CJ20N, PLFAZ, PLSEZ, PROJ, project builder , KBA , PS-ST-PB , Project Builder , Problem