Symptom
Ticket's Item is having the work progress status as Not Relevant.
Environment
SAP Cloud for Customer .
Reproducing the Issue
-
Go to the Service work center.
-
Go to the Tickets view.
-
Search for ticket LMN (where LMN represent the ticket name).
-
Open ticket LMN and go to the Items facet .
-
Select Item XX (where XX represents the line-item number).
-
You can see item's Work Progress is showing as Not Relevant for ZABC (where ZABC represent the processing code type).
Cause
You need to select correct configuration in the fine-tune activity for ticket.
Resolution
-
Go to the Business Configuration work center.
-
Go to the Implementation Projects view.
-
Select the project and click on Open Activity List.
-
Search for fine-tune activity name Tickets for Customer Support and open it.
-
Click on hyperlink Maintain Item Processing Code.
-
Here for the ZABC you have to maintain the Assign to Tab as Service.
-
Save the Changes.
-
Now when you add item of type ZABC, the work progress will show as Open, not as Not Relevant.