Symptom

You get this error while approving the base line of the project

Environment

SAP Business ByDesign

Cause

Approver is the Project manager and hence we don't allow to approve his own project's base line so we raise this error.

Note: Reason why the unassigned task was created is because the responsible unit appearing under accounting tab of the header task is not having a manager and hence un assigned task was raised.

Resolution

Assign this base line Approval task to some one else  other than project responsible