SAP Knowledge Base Article - Public

2835018 - Error During Migration of Bills of Operations

Symptom

 During the migration of Bills of Operations, the following error message is displayed during the simulation step:

Simultaneously-used Resources Only Permitted for Multiple Resource

Environment

SAP Business ByDesign - all versions

Reproducing the Issue

  1. Enter Business Configuration work center.
  2. In the Overview view, search for activity Migration of Bills of Operations.
  3. Click on Migrate Bills of Operations Using the Migration Tool.
  4. Select a file from the staging area, and click on Execute Migration -> Step-by-step.
  5. Proceed to the Step 3 - Simulation.
  6. After the simulation is completed, the error message is raised. 

Cause

This error happens because the resources being used in the migration template are not flagged as "Multiple Resources" option.

Resolution

In order to fix this issue, you need to check the respective resource as "Multiple Resources".

To do that, please follow the below steps:

  1. Go to the Supply Chain Design Master Data work center.
  2. Navigate to the Resources view.
  3. Search for the resource ID that is being used in the migration template.
  4. When opening the resource, you can edit the checkbox for "Multiple Resources".

Keywords

, KBA , SRD-CC-MIG-CNT , Migration: Content , How To

Product

SAP Business ByDesign all versions