Symptom
You are unable to finish a change project. You see the following system message: Finish Project: It is not possible to finalize your scope changes; some of your decisions would cause inconsistencies in your fine-tuning settings. Before continuing with your project, you must either reverse the decisions causing inconsistencies and then click Finish again or click Cancel to cancel your changes entirely.
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to Business Configuration work center
- Click on Implementation Project overview
- Click on New
- Click on Select Scenario
- Add country
- Click on the arrow
- Click on OK
- Click on Next until step 4
- Review Status: You have not reviewed all of the decision-relevant questions for your solution scope. For the questions not reviewed, would you like to accept the answers preselected by SAP based on best practices for your country and type of business?
- Click on Accept preselected Answers
- Enter Title
- Click on Finish
- Finish Project: It is not possible to finalize your scope changes; some of your decisions would cause inconsistencies in your fine-tuning settings. Before continuing with your project, you must either reverse the decisions causing inconsistencies and then click Finish again or click Cancel to cancel your changes entirely.
Cause
There could be some missing values in your fine-tuning settings that causes the inconsistences and that are required for your generic country version to function correctly.
Resolution
To find which values need to be re-stored in the system, please open an incident so that support can check the application logs in the backend.
Keywords
Lösung um Szenario erweitern, Projekt schlägt fehl, Änderungsprojekt, Change project, Konflikte in den Elementen, add new country , KBA , AP-RC-BCT , Business Config. Tools (SAP Business ByDesign , Problem