Symptom

You observe that few of the Project IDs are not available for selection in the 'Project Plan Values' report.

Environment

SAP Business Bydesign

Reproducing the Issue

  1. Go to the Project Management work center.
  2. Go to Reports and then the List View.
  3. Click open the Project Plan Values report.
  4. Go to the selection criteria Projects which is a mandatory field.

 You observe that few of the Project IDs are not available for selection in the Project Plan Values report.

Cause

The characteristic Project of Datasource FINCACU03 has the setting "use context" for value help.

This means that only those projects are shown which are part of the transactional data source FINCACU03.

Resolution

In case some business documents exists for these projects, then the value help would show this entries.