Symptom

In the Project Builder or Project Control apps, attempting to delete a project in TECO (Technically complete) status results in the following error message:

Message no. CJ/242  "You cannot delete this project element.  Or
Message no. PSS4_MSG/065 "You cannot delete this project because of the current processing status".

Diagnosis

The project element cannot be deleted for any of the following cases:

  • This project element has been set to released or partially released at least once in the overall lifecycle.
  • This project element has a planned cost assigned to it."


Read more...

Environment

  • SAP ERP Project Systems (PS)
  • SAP S/4HANA, cloud edition

Product

SAP S/4HANA Cloud Public Edition all versions

Keywords

CJ 242, released, PREL, CJ20N, PSS4_MSG/065, You cannot delete this project because of the current processing status , KBA , PS-ST , Structures , PS-FIO , Fiori UI for Project System , How To

About this page

This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).

Search for additional results

Visit SAP Support Portal's SAP Notes and KBA Search.