2850844 - Total value in application Monitor Purchase Contract Items is calculated wrongly

Symptom

In application 'Monitor Purchase Contract Items', if the unit of 'Target Quantity' is different from 'Price Unit', the Total value will be calculated wrongly.

Environment

  • Sourcing and Procurement
  • SAP S/4HANA Cloud Public Edition 1908

Reproducing the Issue

  1. Create purchase contract item and use different Price Unit from the unit of 'Target Quantity'.
  2. Use application 'Monitor Purchase Contract Items' to check the details of the item created in step 1.
  3. Total value of materials is calculated wrongly with Base Unit instead of Price Unit.

Cause

This is a bug SAP development team has figured out.

Resolution

The display issue will be fixed in further release SAP S/4HANA Cloud Public Edition 2002 CE.

Keywords

S4, HANA, Monitor Purchase Contract Items, Price Unit , KBA , CA-GTF-FXU-MM-PUR , Fiori UI by FXU for MM-FIO-PUR , Bug Filed