SAP Knowledge Base Article - Public

2858462 - Change Audit Report for Job Scheduler

Symptom

  • How to create an audit report for all changes made in Job Scheduler?
  • Is it possible to create audit report regarding Job Scheduler?

Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental.

Environment

SAP SuccessFactors HCM Suite

Resolution

The Job Scheduler Requests report shows changes made to scheduled jobs within the Job Scheduler. It does not include changes made through provisioning. For example, it captures actions like creating new jobs.

Pre-requisites:

  • Permission should be enabled to generate the change audit reports.
  • Please follow the steps on Enabling Change Audit before performing the instructions provided below.

It is possible to create an audit report for all changes made to scheduled job requests created in Job Scheduler, such as creation of a new job.

  1. Go to Admin Center > Search for Change Audit Reports
  2. Select the option Create Configuration Data Report > Click on Job Scheduler Requests 

  3. Select the time range you would like to run the audit and click on Submit

  4. The report file will be sent to the Access Reports tab under Change Audit Reports page.

See Also

Keywords

Job Scheduler Request Report, Audit Change, Change Audit, Changes in Jobs, Provisioning, SuccessFactors, Change Audit Report for Job Scheduler, Job owner, Job name, Edit, Update Job, Manage Scheduled Jobs , KBA , LOD-SF-PLT-CHA , Change Audit , How To

Product

SAP SuccessFactors HCM Suite all versions