Symptom
You made adjustment on the Valuation Variant (SSCUI 102607) and you expect that the Cost Estimate result should change according to the change. However, there is no change at all for the result.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Open App Create Material Cost Estimates.
- Input necessary parameters and execute.
- Check the result.
- Make adjustments on Valuation Variant (SSCUI 102607).
- Check result again.
Cause
There is one more SSCUI setting regarding Valuation Variant:
SSCUI 102608 - Define Valuation Variants per Plant
If settings are made on plant level, 102608 has higher priority than 102607.
Resolution
Make adjustment on
SSCUI 102608 - Define Valuation Variants per Plant
Activity name in CBC system is 'Define Valuation Variants per Plant'.
Keywords
Incorrect, not correct, wrong, value, result, CK11N, CK40N, OKKN, Costing Variant, strategy sequence , KBA , CO-PC-PCP-2CL , Product Cost Planning (Public Cloud) , Problem