2861583 - MRP run did not create Purchase Proposals

Symptom

You have ran the MRP run for Product DEF and you observe system did not generate any  supply through purchase proposals. *DEF refers to Product Id

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to Supply Planning Work Center.
  2. Navigate to Products View
  3. Search for Product DEF
  4. Open Product Planning Details
  5. Run planning -->Single BoM Level

Cause

System did not generate any additional supply through Purchase Proposals as Total Net Requirement is equal to Zero which is nothing but Total Demand is equal to Total Supply

Resolution

The objective of MRP run is to match Demand and Supply i.e Total Demand equal to Total Supply and  set Total Net Requirement  to Zero.

Keywords

MRP run did not create Purchase Proposals, Objective of MRP run is to match Demand and Supply i.e Total Demand equal to Total Supply and  set Total Net Requirement  to Zero. , KBA , mrp run did not create purchase proposal , objective of mrp match demand & supply , AP-SDM-MSD , Material Supply and Demand View , Problem