Symptom
You have ran the MRP run for Product DEF and you observe system did not generate any supply through purchase proposals. *DEF refers to Product Id
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to Supply Planning Work Center.
- Navigate to Products View
- Search for Product DEF
- Open Product Planning Details
- Run planning -->Single BoM Level
Cause
System did not generate any additional supply through Purchase Proposals as Total Net Requirement is equal to Zero which is nothing but Total Demand is equal to Total Supply
Resolution
The objective of MRP run is to match Demand and Supply i.e Total Demand equal to Total Supply and set Total Net Requirement to Zero.
Keywords
MRP run did not create Purchase Proposals, Objective of MRP run is to match Demand and Supply i.e Total Demand equal to Total Supply and set Total Net Requirement to Zero. , KBA , mrp run did not create purchase proposal , objective of mrp match demand & supply , AP-SDM-MSD , Material Supply and Demand View , Problem