2863309 - Integration Center - scheduling: Monthly jobs must not be scheduled beyond the 28th day of the month

Symptom

Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental.

You want to schedule an Integration Center job starting every 30th of the month. However, when you try, the following error appears: "Monthly jobs must not be scheduled beyond the 28th day of the month"

Environment

  • SuccessFactors
  • BizX

Reproducing the Issue

  1. Schedule Integration Center job for the 30th day of the month
    30Nov_IC.png
  2. Error appears
    30Nov_ICii.png

Cause

Expected behaviour. The latest allowed day for scheduling is 29th of the month, this is due to February only having 28/29 days

Resolution

Please schedule your jobs with a latest day of 28/29th of the month

Keywords

  • Monthly jobs must not be scheduled beyond the 28th day of the month
  • Integration Center
  • Scheduling
, KBA , LOD-SF-INT-INC , Integration Center , How To

Product

SAP SuccessFactors HCM Core 1908