Symptom
Project is in "In Planning" status and has to be started. However when user tries to release the project, system is triggering error message.
Read more...
Environment
SAP Business ByDesign
Product
SAP Business ByDesign all versions
Keywords
Project, In Planning, Start and Release, The action ACTIVATE is not possible, You cannot start or release a project without an active baseline, Baseline , KBA , data has been changed in parallel sessio , activate is not possible. refresh screen , the action activate is not possible , start or release a project with baseline , AP-PRO , Project Processing , How To