Symptom
You have a certain lead time for transport between two locations, let’s say:
Lead Time = GI + Transport Duration + GR
But sometimes, running optimizer you observe the created order’s lead time is one day shorter than expected.
For example:
Transport Duration = 48 hours
GR duration = 2 days
Order start date = 21/10 – 00:00:00
Order end date = 24/10 - 23:00:00
Seems the lead time is 3 days and 23 hours.
You expect the order end date to be on 25/10 – 00:00:00.
The same is observed in the product view (/SAPAPO/RRP3) when using time zone of location and in the optimizer result log.
Read more...
Environment
- SAP Supply Chain Management (SCM)
- SAP Advanced Planning and Optimization (SCM-APO)
- SAP Supply Chain Management Supply Network Planning (SCM-APO-SNP)
Product
Keywords
/SAPAPO/MSDP_GET_TRANS_SCHED, /SAPAPO/SAPLMSDP_TIME, perform convert_tstmp_utc2local, /SAPAPO/SNPOP, /SAPAPO/SNPOPLOG, timezone, STK, purchase requisition, pur req, sto, stock transfer order, calendar, table, ET_ARC, details, IT_PROCUR, IT_ARCMAT, ET_ARCMAT. , KBA , SCM-APO-SNP-OPT , Optimization of Supply Network Plan , Problem
About this page
This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).Search for additional results
Visit SAP Support Portal's SAP Notes and KBA Search.