Symptom

  • This Knowledge Base Article will explain how Service - Time and Material item type works in sales order.
  • Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental

Environment

SAP Business ByDesign

Resolution

Case 1: With Time Recording.

Enable the scope question in Business Configuration:

Edit Project Scope>Questions>Sales>Selling Products and Services>Sales Orders

0. configuration.png

1. Create and Release the Sales Order.

1. release SO.png

Status of Sales Order changed from In Preparation to Open.

1. SO open.png

2. Release to Service Execution.

Status of Sales Order changed from Open to In Process. Service Status changed to Released.

2. release to SE.png

3. Click Confirm Service Execution from Sales Order.

Error message displayed: Copying referenced sales order item ID 3691-10 for service confirmation is not possible as it is enabled for time recording.

Since Time Recording for Sales Order has been activated, the assigned Service Performer need to accomplish time recording in his/her time for respective Sales Order.

3. error on creating SC.png

4. Log in as delicate service performer via

Home Work Center>Self-Services Overview>Edit Time Sheet>Add Time Entry

4.add time.png

Actions> Release

Back to respective Sales Order> Document Flow>A service confirmation has been automatically generated with status Finished.

4. dow flow.png

5. Submit > Complete Service Execution

Delivery Status changed from In Process to Finished.

Invoice Status changed from Not Relevant to Not Started.

5. complete service execution.png

6. Invoice the Service Confirmation.

6. invoice SC.png

Back to respective Sales Order

All the status stays in Finished.

6. SO completed.png

Case 2. Without Time Recording Enabled.

Edit Project Scope>Questions>Sales>Selling Products and Services>Sales Orders

Uncheck the question: Do you want to record time for sales orders?

z0.configuration.png

1. Release the Sales Order.

z1.release SO.png

2. Release to Service Execution

The Status of Sales Order changed from Open to In Process. Service Status is Released.

z2.release to service.png

3. Confirm Service Execution> Release Service Confirmation With Order Completion

Back to respective Sales Order> Document Flow

Service Confirmation based Invoice Request has been generated.

Delivery Status changed to Finished.

  • If you release Service Confirmation Without Order Completion, you need to manually complete service in Sales Order.
  • If you release Service Confirmation With Order Completion, the Complete Service Execution button will be grey out.

z3.doc flow.png

z3.delivery finished.png

4. Invoice Service Confirmation Invoice Request.

z4.invoice CIR.png

5. Back to respective Sales Order.

The status of Sales Order changed to Completed as well as on the item level.

z5. SO completed.png

Keywords

SECO; Service - Time and Material; Sales Order , KBA , SRD-CRM-ORD , Orders & Contracts , How To

Product

SAP Business ByDesign all versions

Attachments

Sales Order_Service_time and material.pdf