Symptom
The service agent has entered timesheet with respect to project task and released it. The timesheet status shows "In Approval". However, project manager is not able to view this task under Managing My Area-> Approvals view.
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to Managing My Area work center
- Select view Approvals
- There is no task for the service agent time recording approval in this view
Cause
The project time recording approval is not mapped to Managing My Area-> approvals work center.
The time recording approval with respect to project is visible only under Project Management->Approvals-> Time Recordings view.
Resolution
Please go to the above view and select the respective time recording and there you can select approve /reject option.