Symptom
When you try to submit the project base line for approval you get this error
error may also appear as"Action not executed; data has been changed in parallel session"
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to Project management work center
- Go to Baselines view
- Search for respective project
- Select it and click on approval tab and choose submit approval
You will get this errors
Cause
The project type is marked as Obsolete in business configuration
Resolution
- Go to Business configuration work center
- Go to Implementation projects
- Select the relavent project
- Click on Activity tasks button
- Go to fine tune activity
- Search for Project types
- Select the project type used in your project
- Uncheck it under Obsolete column
See Also
Keywords
Unable to release project, error while releasing project , KBA , AP-PRO , Project Processing , Problem
Product