Symptom
When trying to change the status of a project to Completed, the user gets the error "There is still a purchase requisition commitment for WBS XXX".
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Go to the Plan Customer Projects.
- Select a project and click edit.
- Try to change the status to completed.
Cause
There is an open purchase requisition item(s) for one of the WBS elements of the project.
Resolution
Please close the purchase requisitions for the indicated WBS shown in the error message.
Check the app Purchase Requisition Items by Account Assignment to see the purchase requisition items that need to closed.
See Also
Keywords
Purchase Requisition, Completed, WBS, plan customer projects, purchase order, , KBA , project control , f3215 , CA-CPD-SS , S/4HANA Public Cloud – Professional Service Projects , Problem