SAP Knowledge Base Article - Public

2894781 - Error message There is still a purchase requisition commitment for WBS when changing status of project to completed

Symptom

When trying to change the status of a project to Completed, the user gets the error "There is still a purchase requisition commitment for WBS XXX".

Environment

SAP S/4HANA Cloud

Reproducing the Issue

  1. Go to the Plan Customer Projects.
  2. Select a project and click edit.
  3. Try to change the status to completed.

Cause

There is an open purchase requisition item(s) for one of the WBS elements of the project.

Resolution

Please close the purchase requisitions for the indicated WBS shown in the error message.

Check the app Purchase Requisition Items by Account Assignment to see the purchase requisition items that need to closed.

See Also

SAP Help - Purchase Requisition Items by Account Assignment

Keywords