2900086 - Error message when trying to update the baseline version of a Project

Symptom

On Plan Customer Projects when trying to update the baseline version of a project you get the error message Sorry, the plan data couldn't be saved due to errors.

Environment

SAP S/4HANA Cloud Public Edition.

Reproducing the Issue

  1. Go to Plan Customer Projects.
  2. Select a project and click edit.
  3. Go to the versions tab.
  4. Select the work packages and click Update Baseline.

Cause

One of the selected Work Packages is not assigned to a Billing item in the billing tab.

Resolution

Please assign all of the Work Packages of the project to a Billing item.