Symptom
You want to deactivate a Fixed Asset. However, it is not possible to enter a Deactivation Date as the field is grayed out.
Environment
SAP Business ByDesign
Reproducing the Issue
- In the Fixed Assets work center go to the Fixed Assets view.
- Open the respective Fixed Asset via Edit - Master Data.
- In the Life Cycle Data sub-tab you want to enter a Deactivation Date.
But the Deactivation Date column is read-only.
Cause
The Deactivation field is only available for migrated Fixed Assets.
Not migrated Fixed assets with a netbook value higher than zero cannot be deactivated by setting a Deactivation Date. Here, the consistent course of action is to scrap the asset.
Resolution
You need to scrap the Fixed Asset:
For the Fixed Asset choose Manual Postings and select Complete Scrapping, either within the Fixed Asset or from the Fixed Assets view.
See Also
Keywords
Deactivation Date grayed out, 停用日期 , KBA , SRD-FIN-FA , Fixed Assets , Problem