SAP Knowledge Base Article - Public

2903679 - There is no customer project or internal project displayed in app "Mass Changes to project".

Symptom

In app "Mass Changes to project", the customer projects and internal projects are not displayed.
Due to this, customer projects and internal projects cannot be mass changed by this app.

Environment

SAP S/4HANA Cloud Public Edition.

Cause

The app 'Mass Changes to project' was only designed to mass change EPPM projects.
It cannot be used to mass change customer/internal projects.
Currently there is no plan to extend this to customer/internal projects. In the future road map as well this is not defined yet.

Resolution

Use CPM API SC_PROJ_ENGMT_CREATE_UPD_SRV to mass change customer/inernal projects.

Keywords

Mass Changes to project, mass change, customer project, EPPM, CPM, internal project, F3891 , KBA , PPM-FIO , Fiori UI for Portfolio and Project Management , CA-CPD-SS , S/4HANA Public Cloud – Professional Service Projects , Problem

Product

SAP S/4HANA Cloud Public Edition all versions ; SAP S/4HANA Cloud all versions