Symptom
The Project Currency cannot be changed once the project is saved.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Create an enterprise project.
- Remove the project currency then save.
- The project currency cannot be input/changed anymore.
Cause
This is an expected behaviour.
Project currency is derived from the responsible cost center when creating the project.
It cannot be changed after the project is saved.
Resolution
It is considered as on purpose when the field was left to empty.
Keywords
enterprise project, project currency, project control, released, F3215 , KBA , PS-FIO-STR , Fiori UI for Project Systems-Structures , Problem
Product
SAP S/4HANA Cloud Public Edition all versions