Symptom
You change the Cost Center assignment for a Fixed Asset for a specific start date.
When pressing Save an error message appears: 'The action POST is not possible. Refresh the screen and try again. If the problem persists, report an incident.'
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to the Fixed assets work center.
- Navigate to the Fixed assets view.
- Select the Fixed Asset PQR (PQR represents the Fixed asset ID).
- Go to the Master data tab and choose the Basic Data sub-tab.
- Press Add Row and enter the start date, DD-MM-YYYY (DD-MM-YYYY means start date), maintain the cost center DEF (DEF represents the Cost center ID).
- Press Save.
The error message 'The action POST is not possible. Refresh the screen and try again. If the problem persists, report an incident' is displayed.
Cause
1st case: The organizational units DEF is not valid on DD-MM-YYYY.
2nd case: This can also occur if the previous used organizational units end the Validity a day previous to the Date of the transfer.
You can find the validity:
- Go to the Organizational Management work center.
- Select Edit Org Structures.
- Search for the respective Cost Centers in the Org Structure.
- Go to Timilines tab and check the validity From to Validity To.
Resolution
1st Case:
You need to either increase the validity of the organizational unit DEF to enable the Cost Center transfer posting on DD-MM-YYYY.
Or, alternatively, you change the Start Date of the new the cost center assignment for the Fixed Asset.
2nd case:
In this case, you can change the Validity of organizational unit DEF to one day before the transfer day (DD-1).
See Also
Keywords
cost center, fixed asset, action POST is not possible , KBA , the action post is not possible , fixed asset , the action post is not possible. refresh , fixed asset interval , SRD-FIN-FA , Fixed Assets , How To