Symptom
Default Basic start/finish dates are set based on priority. When the priority is changed the basic dates are not adjusted (point 4)
Image/data in this KBA is from SAP internal systems, sample data, or demo systems. Any resemblance to real data is purely coincidental.
Read more...
Environment
- SAP ERP Plant Maintenance (PM)
- SAP R/3
- SAP R/3 Enterprise
- SAP ERP Central Component
- SAP ERP
- SAP Enhancement package for SAP ERP
- SAP Enhancement package for SAP ERP, version for SAP HANA
- SAP S/4HANA, on-premise
- SAP S/4HANA Cloud Private Edition
Product
SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA Cloud Private Edition all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions
Keywords
IW31, IW32, Relative start date, Relative end date, CAUFVD, GSTRP, GLTRP, LACD_DATE , KBA , PM-WOC-MO , Maintenance Orders , How To