Symptom
After setting the status Technical Completed (TECO) to a production order, you can still post confirmations to the order.
Environment
SAP S/4HANA Cloud.
Reproducing the Issue
- Go to Confirm Production Order Operation app.
- Make a confirmation for an order with the status TECO.
- The system will allow the confirmation
Cause
Standard System Behavior.
Resolution
Technical completion means ending a production order from a logistical viewpoint.
The following actions are executed if an order is set to Technically complete.
-
The order is not relevant for MRP planning
-
Reservations are deleted
-
Capacity requirements are deleted
-
Purchase requisitions for external operations or non-stock materials are deleted
-
The order and its operations receive the system status Technically Completed (TECO)
After technical completion you can still make postings for the order. For instance, material withdrawal or a confirmation can be posted if they were previously forgotten.
For more details, please take a look at the SAP Help: Technical Completion of a Production Order
See Also
Keywords
Technical Completion, TECO, S/4HANA Cloud, Production Order, Status, confirmation, Confirm Production Order Operation, app , KBA , PP-SFC-EXE-CON , Confirmation , How To