Symptom
You want to enter budget in the project screen directly but there is no such option in project screen.
Environment
SAP Business ByDesign
Reproducing the Issue
- Go to the Project Management work center.
- Select the Projects view.
- Select any project and click Edit.
- You are unable to find any option to enter budget on the project screen.
Cause
As of now, there is no such field in project screen where you can enter budget directly.
Resolution
You can analyze the planned costs and revenues for the project in detail as follows:
-
In the Cost and Revenue work center, Projects view.
-
In the Project Plan Values report.
See Also
Please go through the help document Project Cost and Revenue Planning.
Keywords
Project Budget, Project cost and revenue, project planning , KBA , project planning , budget , cost and revenue , AP-PRO , Project Processing , How To
Product
SAP Business ByDesign all versions