SAP Knowledge Base Article - Public

2916021 - Production Proposals Automatically Firmed By System

Symptom

You observe that Production Proposals are sometimes "Firmed By System" and sometimes not. You want to know why does this happen.

Environment

SAP Business ByDesign

Reproducing the Issue

  1. Go to the work center Supply Planning.
  2. Select the view Resource Load. 
  3. Show All Resource Loads By Selection. 
  4. Find XYZ (XYZ represents the Resource ID). 
  5. Click the button Open. 
  6. Under the section Details (of Resource Load tab, sub-tab Load Table) you will see that there are Production Proposals with status "Firmed By System".  

Cause

Generally, the manually created (by user) Proposals are firmed and the ones create by MRP Run are not firmed.

However, the status "Firmed By System" applies for those Proposals where the Availability Date is earlier than the Planning Time Fence Period. In such cases the respective Proposal will be set to "Firmed By System" at Resource Load.

Planning Time Fence Period = System Date + Planning Time Fence (defined in the material's Master Data).

Resolution

The system works as designed and this is the expected behaviour.

See Also

 2839021 - Firm Status For Planning Proposals 

Keywords

production proposal, firmed by system, resource load , KBA , AP-SDM , Supply and Demand Matching , How To

Product

SAP Business ByDesign all versions